Thanks so much for providing a great library.
im currently using highcarts gantt resource management (https://www.highcharts.com/demo/gantt/r ... management) for my company's project
2 quick questions!
1. Can i edit my timeline so that i can get it by weeks
ex) Mar 2 Mar 7 Mar 14 Mar 21 Mar 28 ...
instead of week 1, week 2 , week 3 as provided in highcharts GANTT: resource management https://www.highcharts.com/demo/gantt/r ... grid-light
2. i'd like to add background-color for certain days of the week ex) weekends
i added the gridLineWidth property
xAxis: {
gridLineWidth: 1
},
so that i can get a grid but i'd really like to fill up certain days of the week!